The Black Hills Works Chief Drive Duplex project is progressing nicely – footings and walls are poured, engineered fill has been placed, and plumbing undergrounds are underway and scheduled to be completed this week. The floor slab is anticipated to be poured next week, once that is complete C. Eagle crews will begin the exterior/structural framing and roof trusses.